All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Install and commission direct current (DC) machines |
SAQA US ID | UNIT STANDARD TITLE | |||
259188 | Install and commission direct current (DC) machines | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Electrical Infrastructure Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 4 | NQF Level 04 | 8 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard replaces: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
13657 | Install and commission direct current (DC) machines | Level 4 | NQF Level 04 | 8 |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for persons in the Electrical Engineering; Generation; Distribution; Transmission, Construction and Renewable Energy Sector.
A person credited with this unit standard will be able to: This unit standard will contribute to the full development of the learner within the electrical engineering and construction environment by providing recognition, further mobility and transportability within the field of Physical Planning and Construction. The skills, knowledge and understanding demonstrated within this unit standard are essential for social and economic transformation and upliftment within the electrical engineering and construction environment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following knowledge, skills, attitude and/or equivalent:
|
UNIT STANDARD RANGE |
This unit standard applies to persons installing and commissioning DC machines under supervision.
DC machines include but are not limited to: Testing and measuring equipment may include but are not limited to: |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Plan task and select DC machines. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
An action plan is determined and a sequence of operation is planned according to instructions. |
ASSESSMENT CRITERION 2 |
Appropriate test and measuring equipment and hand tools are selected to meet the job requirements. |
ASSESSMENT CRITERION 3 |
Test and measuring equipment is used according to work site procedures. |
ASSESSMENT CRITERION 4 |
DC machines are selected and tested according to work site procedures and statutory requirements. |
ASSESSMENT CRITERION 5 |
The test results are recorded and interpreted according to work site procedures. |
ASSESSMENT CRITERION 6 |
Safety and good housekeeping practices are followed according to work site procedures. |
SPECIFIC OUTCOME 2 |
Install DC machines. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Appropriate tools and personal protective equipment are selected and used according to job instructions. |
ASSESSMENT CRITERION 2 |
DC machines are installed according to work site procedures and statutory requirements. |
ASSESSMENT CRITERION 3 |
Machine mountings are secured according to work site procedures and statutory requirements. |
ASSESSMENT CRITERION 4 |
Safety, good housekeeping and correct environmental practices are followed according to work site procedures. |
SPECIFIC OUTCOME 3 |
Connect DC machines. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Appropriate tools are selected to meet the job requirements. |
ASSESSMENT CRITERION 2 |
Terminations are prepared according to job instructions and statutory requirements. |
ASSESSMENT CRITERION 3 |
Connections are made to ensure that they are mechanical sound and electrically continuous. |
ASSESSMENT CRITERION 4 |
Safety, good housekeeping and correct environmental practices are followed according to work site procedures. |
SPECIFIC OUTCOME 4 |
Commission DC machines. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Appropriate test, measuring equipment and hand tools are selected to meet the job requirements. |
ASSESSMENT CRITERION 2 |
Measuring equipment, testing equipment and hand tools selected are used according to work site procedures. |
ASSESSMENT CRITERION 3 |
Tests are carried out according to work site procedures and statutory requirements. |
ASSESSMENT CRITERION 4 |
Tests are recorded and reported according to work site procedures. |
ASSESSMENT CRITERION 5 |
Faultfinding and rectifying procedures are carried out where applicable according to work site procedures. |
ASSESSMENT CRITERION 6 |
Final testing and commissioning is carried out and documentation completed according to work site procedures. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Knowledge that will help me understand and that I will be able to explain:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems (identification of defects). |
UNIT STANDARD CCFO WORKING |
Work effectively with others (during the installation commissioning and testing of motor control gear). |
UNIT STANDARD CCFO ORGANISING |
Organise and manage oneself (identification and selection of motor control gear). |
UNIT STANDARD CCFO COMMUNICATING |
Communicate (reporting of defects). |
UNIT STANDARD CCFO SCIENCE |
Use science and technology (environmental and personal safety). |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
This unit standard replaces unit standard 13657, "Install and commission direct current (DC) machines", Level 4, 8 credits.
Supplementary Information: Specified Requirements: Specified requirements include legal and legislative specific requirements and are contained in one or more of the following documents: Glossary of terms: Statutory requirements may include but are not limited to: Work site procedures may include but are not limited to Company`s: Manufacturers` specifications may include but are not limited to: > Manufacturers` maintenance manuals. > Manufacturer catalogues. > Company maintenance manuals. Commissioning may include but is not limited to: Context specific: |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 66009 | National Certificate: Diesel Electric and Electric Fitting | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
Elective | 72052 | Further Education and Training Certificate: Electrical Engineering | Level 4 | NQF Level 04 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | ESKOM GENERATION - PALMIET PUMP STORAGE GRABOUW |
2. | KP ACADEMY (PTY) LTD |
3. | POWER SYSTEMS TRAINING, CAPE TOWN |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |