All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Install and terminate Medium Voltage cables |
SAQA US ID | UNIT STANDARD TITLE | |||
259187 | Install and terminate Medium Voltage cables | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Electrical Infrastructure Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 4 | NQF Level 04 | 6 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard replaces: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
113862 | Install and terminate Medium/High Voltage cables | Level 4 | NQF Level 04 | 6 |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for persons in the Electrical Engineering, Distribution and Construction environment.
A person credited with this unit standard will be capable of: This unit standard will contribute to the full development of the learner within the electrical engineering, distribution and construction environment by providing recognition, further mobility and transportability within the field of Physical Planning and Construction. The skills, knowledge and understanding demonstrated within this unit standard are essential for social and economic transformation and up-liftment within the electrical engineering, distribution and construction environment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following knowledge, skills attitude and/or equivalent:
|
UNIT STANDARD RANGE |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Plan to install Medium Voltage cables. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Planning details are determined according to given instructions and project requirements. |
ASSESSMENT CRITERION 2 |
Appropriate wayleaves, drawings and relevant documentation are acquired in accordance with project/job specifications. |
ASSESSMENT CRITERION 3 |
Materials and tools are selected according to project/job requirements. |
ASSESSMENT CRITERION 4 |
Applicable test equipment is selected and checked for functionality. |
ASSESSMENT CRITERION 5 |
Relevant parties are liased with and notified according to worksite procedures. |
SPECIFIC OUTCOME 2 |
Prepare the Medium Voltage cable ways and work areas. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Cable ways to be prepared and obstructions removed according to cable installation specifications. |
ASSESSMENT CRITERION 2 |
The correct cable is identified, obtained and delivered as per project/job requirements. |
ASSESSMENT CRITERION 3 |
The cable is inspected for physical defects prior to installation. |
ASSESSMENT CRITERION 4 |
Ensure that the cable to be worked on is at zero potential by discharging and capped as per safety standards, procedures and work requirements. |
ASSESSMENT CRITERION 5 |
Work area is assessed for unsafe/hazardous conditions according to statutory requirements and safe work procedures (barricading/shoring). |
SPECIFIC OUTCOME 3 |
Install Medium Voltage cables. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Applicable tools and equipment are selected and used safely to meet the requirements of the job. |
ASSESSMENT CRITERION 2 |
Cable is run out and installed in the cableways according to manufacturer`s specifications. |
ASSESSMENT CRITERION 3 |
Where applicable, shoring is removed, cable trenches are backfilled with appropriate sand/soil, cable marker tape installed and soil compacted according to cable installation procedures. |
ASSESSMENT CRITERION 4 |
Where applicable, cables are secured onto cable ways according to cable installation procedures. |
SPECIFIC OUTCOME 4 |
Terminate and connect Medium Voltage cables. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Applicable tools and equipment are selected and used safely to meet the requirements of the job. |
ASSESSMENT CRITERION 2 |
Cable ends are phased, discharged and prepared for terminating according to manufacturer`s specifications. |
ASSESSMENT CRITERION 3 |
Cable gland or end is positioned; assembled and secured according to manufacturer`s specifications. |
ASSESSMENT CRITERION 4 |
Cable cores are visually phased, aligned, made-off, and connected according to Supply Authority's numbering/colour coding and installation specifications. |
ASSESSMENT CRITERION 5 |
Insulation resistance/continuity/phasing and mechanical tests are carried out on cable/completed termination. |
ASSESSMENT CRITERION 6 |
The cable termination box covers/cover plates are installed/closed and where applicable, filled with insulation compounds/resins as per manufacturer`s specifications. |
SPECIFIC OUTCOME 5 |
Complete the work task. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Work site are restored to original condition as per customer agreement. |
ASSESSMENT CRITERION 2 |
Work area is left clear of surplus/waste materials in accordance with environmental requirements. |
ASSESSMENT CRITERION 3 |
Applicable tools and equipment are cleaned and stored according to OHS Act requirements. |
ASSESSMENT CRITERION 4 |
Documentation is completed and submitted according to data management procedures. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Knowledge that will help me understand and that I will be able to explain:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems. |
UNIT STANDARD CCFO WORKING |
Work effectively with others as a member of a team or group. |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively by means of language skills, oral and/or written. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
This unit standard replaces unit standard 113862, "Install and terminate Medium/High Voltage cables", Level 4, 6 credits. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 66009 | National Certificate: Diesel Electric and Electric Fitting | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
Elective | 72052 | Further Education and Training Certificate: Electrical Engineering | Level 4 | NQF Level 04 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | ESKOM GENERATION - PALMIET PUMP STORAGE GRABOUW |
2. | KP ACADEMY (PTY) LTD |
3. | MALAYSIAN SWITCHGEAR DISTRIBUTORS |
4. | POWER SYSTEMS TRAINING, CAPE TOWN |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |