All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Service and test battery |
SAQA US ID | UNIT STANDARD TITLE | |||
8200 | Service and test battery | |||
ORIGINATOR | ||||
SGB Grain | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 01 - Agriculture and Nature Conservation | Secondary Agriculture | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 2 | NQF Level 02 | 5 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2005-04-13 | 2008-04-13 | SAQA 0459/05 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2009-04-13 | 2012-04-13 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
A learner who has achieved this unit standard will be competent in:
Servicing and testing battery to ensure adequate power supply to electrical systems. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
To enter a learning programme for this unit standard or to be assessed against this unit standard, the learner is assumed to have :
o Introduction to Industry. o Lifting equipment. o Tools and equipment. |
UNIT STANDARD RANGE |
The scope of this unit standard deals servicing and testing of battery components including but not limited to: casting, batteryplates, separated plates, terminal posts, filler caps, battery box and battery clamps. Testing includes but is not limited to: specific gravity, load test, three minute charge test, battery leakage and battery charging.
The specific outcomes as reflected in this unit standard are performed without direct supervision, but with access to work-site procedures and operating instructions and manufacturer`s manuals. Quality procedures include but are not limited to : ISO 9000 |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
PLAN AND PREPARE FOR SERVICING AND TESTING BATTERY |
OUTCOME NOTES |
Reading and interpreting job instructions and determining a sequence of operation according to work site procedure.
Identifying, checking and selecting appropriate service tools and equipment according to job requirements. Preparing work area and vehicle according to work site and manufacturer's procedures. Acquiring manufacturer's manuals and / or specifications according to job requirements. Identifying and selecting appropriate personal protective equipment (PPE) and safety equipment according to statutory and jobrelated safety requirements. Liaising and informing affected parties according to work site procedures. Adhering to supervisors instructions and assignments. Determining a sequence of operation according to work-site procedures and statutory requirements. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Job instructions, oral or written, are accurately followed and adhered to. |
ASSESSMENT CRITERION 2 |
2. Purpose of determining a sequence of operation is explained. |
ASSESSMENT CRITERION 3 |
3. All affected parties are informed of results, deviations and corrective actions taken. |
ASSESSMENT CRITERION 4 |
4. Purpose of selecting and using appropriate tools and equipment is explained. |
ASSESSMENT CRITERION 5 |
5. Reasons for adhering to safety and quality procedures. |
ASSESSMENT CRITERION 6 |
6. Consequences of not selecting particular personal protective and safety equipment are explained. |
ASSESSMENT CRITERION 7 |
7. Possible consequences of not preparing work area according work site procedures are explained. |
ASSESSMENT CRITERION 8 |
8. Possible consequences of not inspecting and recording defect conditions are explained. |
ASSESSMENT CRITERION 9 |
9. Reasons for the disposal of scrap material and storage of surplus material are explained. |
ASSESSMENT CRITERION 10 |
10. Documentation and reports are completed. |
ASSESSMENT CRITERION 11 |
11. Restoring work area according to work site procedures. |
SPECIFIC OUTCOME 2 |
SERVICE BATTERY |
OUTCOME NOTES |
Using appropriate tools according to job requirements
Using appropriate personal protective equipment according to safety and manufacturer's procedure Disconnecting battery according to safety and manufacturer's procedure. Handling battery according to safety and quality standards. Inspecting components, recording and reporting defects according to work site procedures. Cleaning battery according to manufacturer's, work-site and safety procedures. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Job instructions, oral or written, are accurately followed and adhered to. |
ASSESSMENT CRITERION 2 |
2. Purpose of determining a sequence of operation is explained. |
ASSESSMENT CRITERION 3 |
3. All affected parties are informed of results, deviations and corrective actions taken. |
ASSESSMENT CRITERION 4 |
4. Purpose of selecting and using appropriate tools and equipment is explained. |
ASSESSMENT CRITERION 5 |
5. Reasons for adhering to safety and quality procedures. |
ASSESSMENT CRITERION 6 |
6. Consequences of not selecting particular personal protective and safety equipment are explained. |
ASSESSMENT CRITERION 7 |
7. Possible consequences of not preparing work area according work site procedures are explained. |
ASSESSMENT CRITERION 8 |
8. Possible consequences of not inspecting and recording defect conditions are explained. |
ASSESSMENT CRITERION 9 |
9. Reasons for the disposal of scrap material and storage of surplus material are explained. |
ASSESSMENT CRITERION 10 |
10. Documentation and reports are completed. |
ASSESSMENT CRITERION 11 |
11. Restoring work area according to work site procedures. |
SPECIFIC OUTCOME 3 |
TEST BATTERY |
OUTCOME NOTES |
Using appropriate testing tools and equipment, work-site and safety procedures
Testing battery according to manufacturer's work-site and safety procedures Recording test results |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Job instructions, oral or written, are accurately followed and adhered to. |
ASSESSMENT CRITERION 2 |
2. Purpose of determining a sequence of operation is explained. |
ASSESSMENT CRITERION 3 |
3. All affected parties are informed of results, deviations and corrective actions taken. |
ASSESSMENT CRITERION 4 |
4. Purpose of selecting and using appropriate tools and equipment is explained. |
ASSESSMENT CRITERION 5 |
5. Reasons for adhering to safety and quality procedures. |
ASSESSMENT CRITERION 6 |
6. Consequences of not selecting particular personal protective and safety equipment are explained. |
ASSESSMENT CRITERION 7 |
7. Possible consequences of not preparing work area according work site procedures are explained. |
ASSESSMENT CRITERION 8 |
8. Possible consequences of not inspecting and recording defect conditions are explained. |
ASSESSMENT CRITERION 9 |
9. Reasons for the disposal of scrap material and storage of surplus material are explained. |
ASSESSMENT CRITERION 10 |
10. Documentation and reports are completed. |
ASSESSMENT CRITERION 11 |
11. Restoring work area according to work site procedures. |
SPECIFIC OUTCOME 4 |
COMPLETE SERVICING AND TESTING PROCEDURE |
OUTCOME NOTES |
Restoring work site to safe and serviceable condition according to statutory requirements.
Disposing off of scrap material and storing surplus material according to statutory requirements and work site procedures. Storing battery in designated area to statutory requirements and work site procedures. Completing and returning reports and documents according to company procedure. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Job instructions, oral or written, are accurately followed and adhered to. |
ASSESSMENT CRITERION 2 |
2. Purpose of determining a sequence of operation is explained. |
ASSESSMENT CRITERION 3 |
3. All affected parties are informed of results, deviations and corrective actions taken. |
ASSESSMENT CRITERION 4 |
4. Purpose of selecting and using appropriate tools and equipment is explained. |
ASSESSMENT CRITERION 5 |
5. Reasons for adhering to safety and quality procedures. |
ASSESSMENT CRITERION 6 |
6. Consequences of not selecting particular personal protective and safety equipment are explained. |
ASSESSMENT CRITERION 7 |
7. Possible consequences of not preparing work area according work site procedures are explained. |
ASSESSMENT CRITERION 8 |
8. Possible consequences of not inspecting and recording defect conditions are explained. |
ASSESSMENT CRITERION 9 |
9. Reasons for the disposal of scrap material and storage of surplus material are explained. |
ASSESSMENT CRITERION 10 |
10. Documentation and reports are completed. |
ASSESSMENT CRITERION 11 |
11. Restoring work area according to work site procedures. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems in the process of determining defects.
Understand the world as a set of related systems by recognizing the relationship of acids to storage of electricity. |
UNIT STANDARD CCFO WORKING |
Work effectively with others while reporting to affected parties. |
UNIT STANDARD CCFO ORGANISING |
Organise and manage oneself when preparing the work area and determining a sequence of operation. |
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information during the inspection of components and parts. |
UNIT STANDARD CCFO COMMUNICATING |
Communicate with others during the process of oral or written reporting. |
UNIT STANDARD CCFO SCIENCE |
Use science and technology in applying operating principles of electricity and batteries. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
UNIT STANDARD NOTES |
VALUES
All learners should demonstrate : |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 14892 | National Certificate: Agricultural Machinery Technician | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2008-09-13 | AgriSETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |