All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Install luminaires |
SAQA US ID | UNIT STANDARD TITLE | |||
258942 | Install luminaires | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Electrical Infrastructure Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 2 | NQF Level 02 | 4 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2026-06-30 | 2029-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard replaces: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
113879 | Install luminaires | Level 2 | NQF Level 02 | 4 |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for persons in the Electrical Engineering, Generation, Distribution, Transmission, Construction and Renewable Energy Sector.
A person credited with this unit standard will be able to: This unit standard will contribute to the full development of the learner within the electrical engineering and construction environment by providing recognition, further mobility and transportability within the field of Physical Planning and Construction. The skills, knowledge and understanding demonstrated within this unit standard are essential for social and economic transformation and upliftment within the electrical engineering and construction environment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following knowledge, skills attitude and/or equivalent:
|
UNIT STANDARD RANGE |
The work done will be according to the appropriate of the following specifications, standards and/or procedures:
Luminaire application may include but is not limited to: Lamps may include but are not limited to: |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Explain the requirements pertaining to the selection and methods of installation. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The reason for selecting specific types and sizes of equipment/components to install luminaires are explained as per SANS 10142-1 requirements. |
ASSESSMENT CRITERION RANGE |
Cable type, cable size, voltage, current, wattage, frequency rating, termination and insulating material requirements. |
ASSESSMENT CRITERION 2 |
The impact of size and type of light fittings are explained as per SANS 10142-1 requirements. |
ASSESSMENT CRITERION 3 |
The method of cable termination is explained as per installation specifications. |
ASSESSMENT CRITERION 4 |
The applicable method of installation is explained as per installation specifications. |
ASSESSMENT CRITERION 5 |
The regulations applicable to the installation of luminaires are explained as per SANS 10142-1 requirements. |
SPECIFIC OUTCOME 2 |
Prepare to install a luminaire. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Appropriate documentation is obtained as per local job requirements. |
ASSESSMENT CRITERION 2 |
Job instructions are communicated with the team leader according to project or customer requirements. |
ASSESSMENT CRITERION 3 |
Personal protective equipment is selected, inspected according to safe work procedures and OHS Act requirements. |
ASSESSMENT CRITERION 4 |
Tools, material, work platforms and equipment are selected and transported to the work site as per local job requirements. |
ASSESSMENT CRITERION RANGE |
Work platforms may include but are not limited to:
|
ASSESSMENT CRITERION 5 |
The work site is examined for hazardous and sub-standard conditions and corrective action taken where necessary according to safe work procedures and critical task analyses. |
ASSESSMENT CRITERION 6 |
The installation specifications are verified according to job plans and customer requirements. |
ASSESSMENT CRITERION 7 |
The consequences of not preparing to install in line with specified requirements are explained with reference to personal and team safety, impact on the environment, production costs and lost time. |
SPECIFIC OUTCOME 3 |
Install the luminaire. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Hazards and risks directly related to installing a luminaire are identified and addressed according to safe work procedures and critical task analyses. |
ASSESSMENT CRITERION 2 |
The luminaire is installed according to manufacturer`s specifications and customer requirements, in accordance with SANS 10142-1. |
ASSESSMENT CRITERION RANGE |
This includes mounting, termination, luminaire wiring and accessories. |
ASSESSMENT CRITERION 3 |
Safety, good housekeeping and correct environmental practices are followed before, during and after performance. |
ASSESSMENT CRITERION 4 |
The consequences of not installing a luminaire in line with specified requirements are explained with reference to personal and team safety, impact on the environment, production costs and lost time. |
SPECIFIC OUTCOME 4 |
Prepare and test the luminaire for operation. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The luminaire is tested to ensure compliance with SANS 10142-1 requirements. |
ASSESSMENT CRITERION 2 |
The luminaire is connected to the power supply and switched on to ensure functionality. |
ASSESSMENT CRITERION 3 |
Tools, material, work platforms and equipment are cleaned, inspected, stored and waste materials disposed of as per storage procedures and environmental standards. |
ASSESSMENT CRITERION 4 |
The feedback report is completed and submitted in time, in compliance with specified requirements for format, contents, accuracy and distribution. |
ASSESSMENT CRITERION 5 |
The consequences of not reporting and performing housekeeping duties in line with specified requirements are explained with reference to personal and team safety, impact on the environment, production costs and lost time. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Knowledge that will help me understand and that I will be able to explain:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems in testing, fault finding, repairing and rectifying faults. |
UNIT STANDARD CCFO WORKING |
Work effectively with others in reporting test results to superior. |
UNIT STANDARD CCFO ORGANISING |
Organise and manage oneself in planning the work and determining a sequence of operation. |
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information obtained during testing, fault finding, repairing and rectifying faults. |
UNIT STANDARD CCFO COMMUNICATING |
Communicate with superior readings obtained, the interpretation and reporting of test results. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
This unit standard replaces unit standard , "Install luminaires", Level 2, 2 credits.
Supplementary Information: Specified requirements include legal and legislative specific requirements and are contained in one or more of the following documents: |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 73313 | National Certificate: Electrical Engineering | Level 2 | NQF Level 02 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | 4 TOPS ACADEMY |
2. | AFRICA SKILLS VILLAGE |
3. | Better Best Agri Development |
4. | BOLAND COLLEGE (Paarl) |
5. | Double ST Training and Skills Development |
6. | ESKOM GENERATION - PALMIET PUMP STORAGE GRABOUW |
7. | Goitsebasadi Construction Project |
8. | KP ACADEMY (PTY) LTD |
9. | Majuba TVET College |
10. | MSC ARTISAN ACADEMY |
11. | PCD College cc |
12. | POWER SYSTEMS TRAINING, CAPE TOWN |
13. | Protech Training (Pty) Ltd |
14. | Umfolozi FET College |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |