All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Lay pipes for water and wastewater reticulation systems |
SAQA US ID | UNIT STANDARD TITLE | |||
254070 | Lay pipes for water and wastewater reticulation systems | |||
ORIGINATOR | ||||
SGB Water Sector | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Civil Engineering Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 12 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2026-06-30 | 2029-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard replaces: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
12338 | Lay pipes for water reticulation system | Level 3 | NQF Level 03 | 12 | |
115904 | Lay pipes for a wastewater reticulation system | Level 3 | NQF Level 03 | 10 |
PURPOSE OF THE UNIT STANDARD |
The qualifying learner achieving this unit standard will be able to undertake specific pipe laying tasks on a water and waste water reticulation system to the requirements of an engineering drawing. This competence will enable the learner to work on an urban or rural reticulation project. Achieving this unit standard will enhance the employability of the qualifying learner in the water and wastewater and other related sectors. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
UNIT STANDARD RANGE |
Resources: Labour, pipes, associated fittings, valves, meters, cathodic devices, tools, plant, construction materials.
Personal safety equipment: Gloves, goggles, overalls, boots, mask, earplugs, helmet, torch, breathing aids, gumboots. Safety equipment: Barricading, signage and all other items and materials used to ensure the safety of personnel, passers-by and traffic. Thrust blocks: Concrete; reinforced concrete; prefabricated thrust blocks. Manhole and chambers: Pre-constructed, re-enforced concrete constructed and brick built. Records and reports: Time sheets, log books, accident reports, injury reports, incident reports, daily meter reading data, job cards, "As built" plans (Deviations from engineering drawings), patching reports (e.g. tarmac or concrete surfaces). |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Set out a pipe route using control points. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The route of the pipeline is checked for availability in terms of other services and surface use. |
ASSESSMENT CRITERION RANGE |
All underground services, traffic use, surface cover options. |
ASSESSMENT CRITERION 2 |
The route of the pipeline is set out using, centre line or offset marks in terms of plan position. |
ASSESSMENT CRITERION 3 |
Vertical alignment is set out in accordance with engineering drawing. |
ASSESSMENT CRITERION RANGE |
Sight rails, laser, dumpy level, line. |
SPECIFIC OUTCOME 2 |
Check and form trench sub-grade and base in preparation for pipe installation. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The trench sub-grade is checked for soft spots in terms of the specification. |
ASSESSMENT CRITERION RANGE |
One of visual, bearing, penetrometer tests. |
ASSESSMENT CRITERION 2 |
Any soft spots in the trench sub-grade are corrected in terms of the specification. |
ASSESSMENT CRITERION 3 |
The sub-grade level is checked in terms of the specification. |
SPECIFIC OUTCOME 3 |
Lay pipeline in accordance with code of practice and engineering drawing. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Tasks are communicated to work team. |
ASSESSMENT CRITERION 2 |
Bedding sand is laid in accordance with specifcations. |
ASSESSMENT CRITERION RANGE |
Class of bedding. |
ASSESSMENT CRITERION 3 |
Pipes are aligned on bedding sand in accordance with alignment requirements. |
ASSESSMENT CRITERION 4 |
New pipeline is linked to mains and isolated. |
ASSESSMENT CRITERION 5 |
Pipes are joined in accordance with specifications. |
ASSESSMENT CRITERION 6 |
Cathodic devices are attached to pipes if required. |
ASSESSMENT CRITERION 7 |
Valves, meters and other fittings are connected to pipes. |
ASSESSMENT CRITERION 8 |
Thrust blocks are placed in correct positions. |
ASSESSMENT CRITERION 9 |
Pipes are partially covered with bedding sand exposing joints until pressure testing is complete. |
SPECIFIC OUTCOME 4 |
Inspect and test the system in accordance with code of practice. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Tasks are communicated to work team. |
ASSESSMENT CRITERION 2 |
Pipe system is inspected and tested in accordance with specifications and procedure. |
ASSESSMENT CRITERION RANGE |
Pressure (water and/or air), Alignment (Mirror test), Integrity (CCTV). |
ASSESSMENT CRITERION 3 |
Problems are identified and corrective action is explained and demonstrated. |
ASSESSMENT CRITERION 4 |
System is disinfected where required. |
ASSESSMENT CRITERION 5 |
Pipes are scoured and filled with water. |
SPECIFIC OUTCOME 5 |
Complete final backfill and construction work as per code of practice and specification. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Tasks are communicated to work team. |
ASSESSMENT CRITERION 2 |
Blanket sand is laid over pipes according to work place standard operating procedures. |
ASSESSMENT CRITERION RANGE |
Haunching, encasement, sand blanket. |
ASSESSMENT CRITERION 3 |
Manholes and chambers are constructed according to plan. |
ASSESSMENT CRITERION 4 |
Shoring is removed. |
ASSESSMENT CRITERION 5 |
Backfilling of trench is completed according to work place standard operating procedures. |
ASSESSMENT CRITERION 6 |
Area is rehabilitated in accordance with work policies. |
ASSESSMENT CRITERION 7 |
All safety equipment and other resources are removed and returned to stores. |
SPECIFIC OUTCOME 6 |
Shut down and charge system in accordance with code of practice and work procedures. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Purpose of shut down procedure is explained. |
ASSESSMENT CRITERION 2 |
Valves to be isolated are identified as per engineering drawings or visual inspection and in terms of reason for shut down. |
ASSESSMENT CRITERION 3 |
Identified valves are isolated. |
ASSESSMENT CRITERION 4 |
Purpose of charging procedure is explained. |
ASSESSMENT CRITERION 5 |
Section of system to be charged is identified. |
ASSESSMENT CRITERION 6 |
Valves to be opened are identified as per engineering drawings or by visual inspection. |
ASSESSMENT CRITERION 7 |
Identified valves are opened as per code of practice procedure. |
SPECIFIC OUTCOME 7 |
Complete reports and records in accordance with work procedures. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Reports and records are maintained or completed accurately. |
ASSESSMENT CRITERION 2 |
Reports and records are handed to appropriate persons. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Learners are to have a knowledge and understanding of:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems in which responses display that responsible decisions using critical and creative thinking have been made.
This relates to: |
UNIT STANDARD CCFO WORKING |
Work effectively with others as a member of a team, group, organisation, and community.
This relates to: |
UNIT STANDARD CCFO ORGANISING |
Plan, organise and manage oneself and one`s activities responsibly and effectively.
This relates to: |
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information.
This relates to: |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively using visual, mathematical and/or language skills in the form of oral and/or written presentation.
This relates to: |
UNIT STANDARD CCFO SCIENCE |
Use science and technology effectively and critically, showing responsibility towards the environment and health of others.
This relates to: |
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrate an understanding of the world as a set of related systems by recognising that problem-solving contexts do not exist in isolation.
This relates to: |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
This Unit Standard replaces the following Unit Standards:
|
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 60155 | National Certificate: Water and Wastewater Reticulation Services | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | EWSETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | CHILUTSI TRADING ENTERPRISE |
2. | ERGO MAPHELONG INSTITUTE (PTY) LTD |
3. | ERWAT |
4. | HAZYVIEW WATER SKILLS ACADEMY |
5. | SEANEGO INTERGRATED NATURAL RESOURCES MANAGEMENT |
6. | THOBOLOGO TRAINING & EDUCATION GROUP |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |