All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Repair rail-manufactured frogs |
SAQA US ID | UNIT STANDARD TITLE | |||
120442 | Repair rail-manufactured frogs | |||
ORIGINATOR | ||||
SGB Manufacturing and Assembly Processes | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 06 - Manufacturing, Engineering and Technology | Engineering and Related Design | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 23 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for a learner within the fabrication and welding fields. Learners credited with this unit standard will be able to repair rail-manufactured frogs safely by means of welding, grinding and cutting processes to a high degree of accuracy in accordance with required quality specifications and standards.
The qualifying learner is capable of: |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
It is assumed that learners are already competent in:
> "Operate rail disc cutting equipment " > "Operate rail-grinding equipment " > "Grind rails with rail grinding equipment" > "Cut rails of various profiles and grades" > "Operate hydraulic rail shearing machine" > "Shear rails" > "Cut rail of various profiles and grades" |
UNIT STANDARD RANGE |
The level assigned to this unit standard is appropriate because, performance may be carried out:
This unit standard is exclusive of chrome-manganese rails, mono block crossings and rail-bound turnouts. |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Plan and prepare machines, equipment and resources prior to the repairing of rail-manufactured frog. |
OUTCOME RANGE |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Equipment, tools, consumables and fire-fighting equipment are obtained, verified, loaded and off- loaded in accordance in accordance with Permanent way welding specifications. |
ASSESSMENT CRITERION 2 |
The correct personal protective equipment is identified, obtained and used at all times as required. |
ASSESSMENT CRITERION 3 |
The necessary precautions are taken to prevent injury to personnel when working with Perway and welding equipment according to Permanent way specifications. |
ASSESSMENT CRITERION 4 |
Vehicle inspection is done in accordance with company procedures and specifications. |
ASSESSMENT CRITERION RANGE |
Road Transport Act. |
SPECIFIC OUTCOME 2 |
Plan and prepare for the repairing of rail-manufactured frogs according to company specifications and procedures. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Fire hazards are identified, limited or removed according to company specifications. |
ASSESSMENT CRITERION 2 |
On-track protection is placed correctly and timeously according to Permanent way welding specifications. |
ASSESSMENT CRITERION 3 |
Roll marks on rails are identified correctly and the applicable work procedure(s) are applied. |
ASSESSMENT CRITERION 4 |
Rail-manufactured frogs are measured, location is logged and specific repair process is determined correctly. |
ASSESSMENT CRITERION 5 |
Frogs are cleaned and checked for cracks by means of non-destructive tests according to Permanent way welding specifications. |
ASSESSMENT CRITERION 6 |
Preparatory grinding/cutting to remove loose metal and cracks on the crown and splice rail is performed safely and correctly according to Permanent way welding specifications. |
ASSESSMENT CRITERION 7 |
Area to be welded is measured and marked out according to company procedures and specifications. |
ASSESSMENT CRITERION 8 |
Non-destructive testing is performed correctly in accordance with specified company procedures and specifications. |
SPECIFIC OUTCOME 3 |
Repair rail-manufactured frog. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Extremities of defect in the rail are measured and marked out correctly according to company procedures and specifications. |
ASSESSMENT CRITERION 2 |
All bolts on the frog and sleeper fastenings are loosened off according to company procedures. |
ASSESSMENT CRITERION 3 |
Preheating process is performed safely and correctly according to company procedures and specifications. |
ASSESSMENT CRITERION 4 |
The welding process is performed safely and correctly according to company-specific procedures and specifications. |
ASSESSMENT CRITERION 5 |
Grinding process is performed safely and correctly according to company-specific procedures and specifications. |
ASSESSMENT CRITERION 6 |
Cutting process is performed safely and correctly according to company-specific procedures and specifications. |
ASSESSMENT CRITERION 7 |
Measurements are taken to ensure that rail-manufactured frog conforms to specified tolerances as per company-specific specifications. |
ASSESSMENT CRITERION 8 |
Equipment, tools and consumables are removed from track safely and correctly and work area is cleaned in accordance with company and legislative safety policies, procedures and specifications. |
ASSESSMENT CRITERION 9 |
Non-destructive tests are performed correctly in accordance with company-specified procedures and specifications. |
ASSESSMENT CRITERION 10 |
Information on register block is recorded safely and correctly in accordance with company- specified procedures and specifications. |
SPECIFIC OUTCOME 4 |
Compile the relevant technical documentation. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Work orders and instructions are interpreted and understood in accordance with company's policies and procedures. |
ASSESSMENT CRITERION 2 |
All documentation is completed accurately and timeously according to company procedures. |
ASSESSMENT CRITERION 3 |
Information is reported to the relevant parties in line with the set standards. |
ASSESSMENT CRITERION 4 |
The completed documentation is administered in accordance with company's policies and procedures. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Learners can understand and explain:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Problem solving
Learners have the generic ability to identify and solve problems with regard to: |
UNIT STANDARD CCFO WORKING |
Teamwork
Learners can work effectively in teams when: |
UNIT STANDARD CCFO ORGANISING |
Self-organisation and -management
Learners can organise and manage oneself by: |
UNIT STANDARD CCFO COLLECTING |
Information Evaluation
Learners can evaluate information: |
UNIT STANDARD CCFO COMMUNICATING |
Learners can communicate effectively:
|
UNIT STANDARD CCFO SCIENCE |
Learners can use science and technology by:
|
UNIT STANDARD CCFO DEMONSTRATING |
Interrelatedness of systems
Learners can understand that, by eliminating the dynamic effects in the frog, the life-span of the components and track structure is enhanced, thus contributing to the safe passage of rail traffic. |
UNIT STANDARD CCFO CONTRIBUTING |
Learner and societal development
Learners can understand the importance of: |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
Supplementary information:
Rail vehicles include all trains and other on-track inspection and maintenance vehicles capable of travelling on railway track. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 49795 | National Certificate: Rail Construction and Maintenance | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | TETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | R and H Rail (Pty) Ltd |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |