All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Repair 14% cast manganese frogs |
SAQA US ID | UNIT STANDARD TITLE | |||
120439 | Repair 14% cast manganese frogs | |||
ORIGINATOR | ||||
SGB Manufacturing and Assembly Processes | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 06 - Manufacturing, Engineering and Technology | Fabrication and Extraction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 4 | NQF Level 04 | 34 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for a learner within the fabrication and welding fields. Learners credited with this unit standard will be able to repair 14% cast manganese frogs safely and to a high degree of accuracy in accordance with required quality specifications and standards by means of welding, grinding and gouging processes.
The qualifying learner is capable of: |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
It is assumed that learners are already competent in:
The following unit standards at NQF Level 3: |
UNIT STANDARD RANGE |
Performance may be carried out.
This unit standard is inclusive of chrome-manganese rails and rail-bound frogs. This unit standard is exclusive of rail-manufactured frogs. |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Plan and prepare machines, equipment and resources prior to the repairing of 14% cast manganese frogs. |
OUTCOME RANGE |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Equipment, tools, consumables and correct fire-fighting equipment are obtained, verified, loaded and off-loaded in accordance with Permanent way welding specifications. |
ASSESSMENT CRITERION 2 |
The correct personal protective equipment is identified, obtained and used at all times as required. |
ASSESSMENT CRITERION 3 |
The necessary precautions are taken to prevent injuries of personnel when working with Perway and welding equipment according to Permanent way specifications. |
ASSESSMENT CRITERION 4 |
Vehicle inspection is done in accordance with company procedures and specifications. |
ASSESSMENT CRITERION RANGE |
Road Transport Act. |
SPECIFIC OUTCOME 2 |
Plan and prepare for the repairing of 14% cast manganese frogs in accordance with permanent way specifications. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Fire hazards are identified, limited or removed according to standard practice. |
ASSESSMENT CRITERION 2 |
Applicable fire-fighting equipment is placed in the work area safely and correctly according to company policies, procedures and specifications. |
ASSESSMENT CRITERION 3 |
On-track protection is placed correctly and timeously according to company-specific instructions. |
ASSESSMENT CRITERION 4 |
14% Cast manganese frogs are measured, location is logged and specific repair process is determined correctly. |
ASSESSMENT CRITERION 5 |
Frogs are cleaned and checked for cracks by means of non-destructive tests. |
ASSESSMENT CRITERION 6 |
Preparatory work is done in accordance with company procedures and instructions. |
ASSESSMENT CRITERION RANGE |
Grinding/gouging/pre-stressing. |
ASSESSMENT CRITERION 7 |
All fastenings are secured in accordance with company procedures and specifications. |
ASSESSMENT CRITERION 8 |
Area to be welded is measured and marked out correctly according to Permanent way welding specifications. |
ASSESSMENT CRITERION 9 |
Non-destructive testing is performed correctly and in accordance with specified welding procedures and specifications. |
SPECIFIC OUTCOME 3 |
Repair 14% cast manganese frog safely and correctly in accordance with company procedures and specifications. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Extremities of defect on the rail are measured and marked out correctly. |
ASSESSMENT CRITERION 2 |
Sleeper fastenings are loosened in accordance with company procedures and instructions. |
ASSESSMENT CRITERION 3 |
Welding procedure is performed safely and correctly according to company specific specifications. |
ASSESSMENT CRITERION 4 |
Gouging process is performed safely and correctly according to company-specific procedures and specifications. |
ASSESSMENT CRITERION 5 |
Measurements are taken to ensure that 14% cast manganese frog conforms to specified tolerances as per company-specific specifications. |
ASSESSMENT CRITERION 6 |
Equipment, tools and consumables are removed from track and work area is cleaned in accordance with company procedures and specifications. |
ASSESSMENT CRITERION 7 |
Information on register block is recorded safely and correctly in accordance with company procedures and specifications. |
SPECIFIC OUTCOME 4 |
Complete the relevant technical documentation. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Work orders and instructions are interpreted and understood in accordance with company's policies and procedures. |
ASSESSMENT CRITERION 2 |
Information is reported to the relevant parties in line with the set standards. |
ASSESSMENT CRITERION 3 |
The completed documentation is administered in accordance with company's policies and procedures. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Learners can understand and explain:
1. The purpose, function and use of measuring equipment. 2. District asset diagram reading. 3. The purpose, function and operation of tools and equipment. 4. The purpose, function, identification and use of consumables. 5. Act 85 related to applicable equipment and machines used. 6. Lifting equipment (Code of Practice No 29 & 30). 7. The stowage of equipment. 8. Track maintenance instructions and specifications related to the repairing of 14% cast manganese frogs. 9. Track welding specifications related to the repairing of 14% cast manganese frogs. 10. The safe work procedures related to 14% cast manganese frogs. 11. Basic electricity. 12. The purpose, function and use of personal protective equipment. 13. Frog identification (Cast marks). 14. The parameters of limits as stated in specification for the length and depth of defects. 15. Crack detection by non-destructive test. 16. The identification, purpose and use of all fastenings. 17. 14% Cast manganese frog welding processes, procedures and specifications. 18. Stencilling. 19. Coding. |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Learners have the generic ability to identify and solve problems with regard to:
|
UNIT STANDARD CCFO WORKING |
Learners can work effectively in teams when:
|
UNIT STANDARD CCFO ORGANISING |
Learners can organise and manage one-self by:
|
UNIT STANDARD CCFO COLLECTING |
Learners can evaluate information:
|
UNIT STANDARD CCFO COMMUNICATING |
Learners can communicate effectively:
|
UNIT STANDARD CCFO SCIENCE |
Learners can use science and technology by:
|
UNIT STANDARD CCFO DEMONSTRATING |
Learners can understand that, by eliminating the dynamic effects on the frog, the life-span of the component and track structure is enhanced, thus contributing to the safe passage of rail traffic. |
UNIT STANDARD CCFO CONTRIBUTING |
Learners can understand the importance of:
|
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
Values:
Supplementary information: Rail vehicles include all trains and other on-track inspection and maintenance vehicles capable of travelling on railway track. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 49795 | National Certificate: Rail Construction and Maintenance | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | TETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | R and H Rail (Pty) Ltd |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |