SAQA All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source.
SOUTH AFRICAN QUALIFICATIONS AUTHORITY 
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: 

Use a mobile crane to carry out demolition activities with demolition equipment 
SAQA US ID UNIT STANDARD TITLE
116989  Use a mobile crane to carry out demolition activities with demolition equipment 
ORIGINATOR
SGB Civil Engineering Construction 
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY
-  
FIELD SUBFIELD
Field 12 - Physical Planning and Construction Civil Engineering Construction 
ABET BAND UNIT STANDARD TYPE PRE-2009 NQF LEVEL NQF LEVEL CREDITS
Undefined  Regular  Level 3  NQF Level 03 
REGISTRATION STATUS REGISTRATION START DATE REGISTRATION END DATE SAQA DECISION NUMBER
Passed the End Date -
Status was "Reregistered" 
2018-07-01  2023-06-30  SAQA 06120/18 
LAST DATE FOR ENROLMENT LAST DATE FOR ACHIEVEMENT
2024-06-30   2027-06-30  

In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise.  

This unit standard does not replace any other unit standard and is not replaced by any other unit standard. 

PURPOSE OF THE UNIT STANDARD 
The qualifying learner is capable of:

Demonstrating knowledge of the functions of demolition equipment used with mobile cranes, preparing cranes for demolition service; performing demolition and other similar activities; and re-rigging and functionally testing cranes for routine mobile crane use, and completing documentation.

The contribution to The National Skills Development Strategy is the key developmental interface between learners and new competencies to be achieved.

Learners who master the applied competence described in this unit standard will contribute to the development of a professional community of Civil Engineering Construction Crane Operators who are able to competently use science and technology when applying operation techniques.

The contribution to socio-economic transformation is that learners will be able to undergo RPL-assessment and thereby receive recognition for previous learning and experience. This in turn will enhance the employability and career prospects of learners employed in this sector. 

LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING 
The following knowledge, skills attitude and/or equivalent:
  • NQF Level 2 Numeracy and NQF Level 2 Literacy
  • Prerequisite Unit Standard: Operate a Mobile Crane NQF Level 3 

  • UNIT STANDARD RANGE 
    Preparation of worksite includes but is not limited to:
  • Levelling ground, checking soil conditions, establishing positions of existing services.

    Factors influencing safety and suitability of a crane:
  • Stability
  • Suitability
  • State of repair
  • Proximity of other machines and workers

    Statutory requirements include but are not limited to:
  • Relevant Code of practice
  • Safety, Health & Environmental legislation
  • Local Provincial authority requirements

    Further Specific range statements are provided in the body of the unit standard where they apply to particular specific outcomes or assessment criteria. 

  • Specific Outcomes and Assessment Criteria: 

    SPECIFIC OUTCOME 1 
    Plan work activity. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    Job instructions are interpreted correctly and a sequence of operations is determined according to worksite procedures. 
    ASSESSMENT CRITERION RANGE 
    Worksite procedures include but are not limited to manufacturer's procedures, Crane operation manuals and site operational requirements
     

    ASSESSMENT CRITERION 2 
    Plans are developed to eliminate, avoid/neutralise all identified risks in accordance with safety regulations, legislation and site specific instructions. 

    ASSESSMENT CRITERION 3 
    All tools and attachments required for the work activity are selected and checked to be functional and ready for use according to job requirements. 
    ASSESSMENT CRITERION RANGE 
    Crane attachments include all permanent and removable standard components.
     

    ASSESSMENT CRITERION 4 
    Alternative or complementary equipment is identified in terms of the required task. 
    ASSESSMENT CRITERION RANGE 
    Alternative/complimentary equipment includes all equipment that could be used to perform the same or similar tasks.
     

    ASSESSMENT CRITERION 5 
    Affected parties are informed and liaised with according to worksite procedures. 

    ASSESSMENT CRITERION 6 
    The consequences of not liaising with the appropriate parties are explained in terms of disruption to work. 

    SPECIFIC OUTCOME 2 
    Prepare work area. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    Work area is inspected and prepared according to worksite procedures. 
    ASSESSMENT CRITERION RANGE 
    Worksite procedures include but are not limited to manufacturer's procedures, operators manuals and site operational requirements.
     

    ASSESSMENT CRITERION 2 
    Reasons for inspections and preparation are defined in terms of safety and work flow. 

    ASSESSMENT CRITERION 3 
    Safety of working area is ensured according to statutory requirements. 
    ASSESSMENT CRITERION RANGE 
    Statutory requirements include but are not limited to
    i. OHS Act,
    ii. Environmental legislation,
    iii. Local Provincial authority requirements
    iv. Code of Practice
     

    ASSESSMENT CRITERION 4 
    Descriptions of the procedures to be followed to ensure the safety of the work area are described in terms of the elimination of potential hazards. 

    ASSESSMENT CRITERION 5 
    Personal Protective Equipment is used according to statutory requirements. 

    ASSESSMENT CRITERION 6 
    The consequences of not correctly using Personal Protective Equipment are explained in terms of potential danger to self and others. 

    SPECIFIC OUTCOME 3 
    Prepare crane for demolition service. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    Crane is confirmed as suitable for demolition services in accordance with the crane manufacturer's operating manual, the company policy and procedures for use of cranes, and recognised standards. 

    ASSESSMENT CRITERION 2 
    Crane is rigged for demolition service in accordance with recognised standards for demolition work. 

    ASSESSMENT CRITERION 3 
    Siting of the crane and the sequence of procedures are planned in consultation with customer and/or authorised personnel. 

    ASSESSMENT CRITERION 4 
    Safety precautions are taken and hazard control measures implemented in accordance with plan of work, prior to commencement of demolition activities. 
    ASSESSMENT CRITERION RANGE 
    Ropes, reeving, chains, balls, boom attachments, magnets.
     

    ASSESSMENT CRITERION 5 
    Consequences of unsafe acts are explained in terms of the potential effect on the safety of self and others and penalties imposed. 

    SPECIFIC OUTCOME 4 
    Perform demolition activities. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    Crane is operated in accordance with crane manufacturer's operating instructions for demolition, or other similar service and recognised standards. 
    ASSESSMENT CRITERION RANGE 
    Demolition, dropping, throwing operations.
     

    ASSESSMENT CRITERION 2 
    Hazard control is implemented in accordance with hazard control strategies. 
    ASSESSMENT CRITERION RANGE 
    Stability of crane, failure of ropes, ball or load.
     

    ASSESSMENT CRITERION 3 
    Signals are given and interpreted in accordance with planned procedures and the Power Crane Association Safety Manual. 

    ASSESSMENT CRITERION 4 
    Daily servicing is carried out in accordance with company procedures. 

    SPECIFIC OUTCOME 5 
    Re-rig and functionally test crane for routine mobile crane use. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    Crane is re-rigged for routine mobile crane use in accordance with crane manufacturer's instructions and company procedures. 

    ASSESSMENT CRITERION 2 
    Test in accordance with crane manufacturer's instructions and company procedures, prior to the crane being returned to other mobile crane activities. 


    UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS 
  • Anyone assessing a learner or moderating the assessment of a learner against this unit standard must be registered as an assessor with the CETA-ETQA.
  • Any institution offering learning that will enable the achievement of this unit standard must be accredited as a provider with the CETA-ETQA.
  • CETA-ETQA or other ETQA's who have a Memorandum of Understanding in place with CETA-ETQA would be responsible for moderation of learner achievements of learners who meet the requirements of this qualification. 

  • UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE 
  • Mobile crane operating procedures and main functions of all major components and systems
  • The maximum operating capacities of the designed working capabilities.
  • Statutory requirements including the Relevant Code of practice and Safety, Health & Environmental legislation
  • The functions of demolition equipment
  • Recognized hand signals (and other methods of communication) to direct the crane movements.
  • Selection of crane against environmental restraints. 

  • UNIT STANDARD DEVELOPMENTAL OUTCOME 
    N/A 

    UNIT STANDARD LINKAGES 
    N/A 


    Critical Cross-field Outcomes (CCFO): 

    UNIT STANDARD CCFO IDENTIFYING 
    Identify and solve problems.

    Evident in Specific Outcome:
  • Perform demolition activities

    Evident in Assessment Criteria:
  • Hazard control is implemented in accordance with hazard control strategies. 

  • UNIT STANDARD CCFO WORKING 
    Work effectively with others.

    Evident in Specific Outcome:
  • Plan work activity

    Evident in Assessment Criteria:
  • The consequences of not liaising with the appropriate parties are explained in terms of disruption to work. 

  • UNIT STANDARD CCFO ORGANISING 
    Employ self-management.

    Evident in Specific Outcome:
  • Prepare crane for demolition service

    Evident in Assessment Criteria:
  • Siting of the crane and the sequence of procedures are planned in consultation with customer and/or authorised personnel. 

  • UNIT STANDARD CCFO COLLECTING 
    Manage information.

    Evident in Specific Outcome:
  • Plan work activity

    Evident in Assessment Criteria:
  • Job instructions are interpreted correctly and a sequence of operations is determined according to worksite procedures. 

  • UNIT STANDARD CCFO COMMUNICATING 
    Communicate effectively.

    Evident in Specific Outcome:
  • Plan work activity

    Evident in Assessment Criteria:
  • Affected parties are informed and liaised with according to worksite procedures. 

  • UNIT STANDARD CCFO SCIENCE 
    Demonstrate scientific and technological competence.

    Evident in Specific Outcome:
  • Prepare crane for demolition service

    Evident in Assessment Criteria:
  • Crane is confirmed as suitable for demolition services in accordance with the crane manufacturer's operating manual, the company policy and procedures for use of cranes, and recognised standards. 

  • UNIT STANDARD CCFO DEMONSTRATING 
    Understand contextual world-systems.

    Evident in Specific Outcome:
  • Prepare work area

    Evident in Assessment Criteria:
  • Safety of working area is ensured according to statutory requirements. 

  • UNIT STANDARD ASSESSOR CRITERIA 
    N/A 

    REREGISTRATION HISTORY 
    As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. 

    UNIT STANDARD NOTES 
    N/A 

    QUALIFICATIONS UTILISING THIS UNIT STANDARD: 
      ID QUALIFICATION TITLE PRE-2009 NQF LEVEL NQF LEVEL STATUS END DATE PRIMARY OR DELEGATED QA FUNCTIONARY
    Elective  49080   National Certificate: Construction: Advanced Crane Operations  Level 3  NQF Level 03  Passed the End Date -
    Status was "Reregistered" 
    2023-06-30  CETA 
    Elective  64829   National Certificate: Lifting Machine Operations  Level 3  NQF Level 03  Passed the End Date -
    Status was "Reregistered" 
    2023-06-30  TETA 


    PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: 
    This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here.
     
    1. imithetho labour law 
    2. Tjeka Training Matters Pty Ltd 
    3. Transvaal Training 



    All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source.